Please view the most recent aerial video of the progress made at the new high school site, taken on July 6, 2019. The past week’s work included: completion of interior wall framing in level 1 and starting of wall framing in level 2, sheet rocking of main electrical room, completion of theater control room conduit under slab connections, as well as framing and sheathing of exterior walls.