Please view the most recent aerial video of the progress made at the new high school site, taken on May 9, 2020. The past week’s work included: completion of the exterior brick veneer on the building, completion of seating in the theater, striping and landscape in the NE parking lot, as well as the start of final cleaning in classrooms.